Engineering Command Center

Projects, permits, inspections, contractors and engineering performance.

Municipal Engineering Operations

Current projects, permit applications, inspections and implementation status.

2026 Engineering Performance

One engineering workspace for infrastructure delivery, permits and field inspections.

The municipality currently has 28 active projects, 142 building permit applications under processing, and 36 inspections scheduled this week. Overall project accomplishment is 74% against the year-to-date target.

28Active Projects
142Permit Applications
36Inspections This Week
74%Project Accomplishment
46Total Projects
28Ongoing Projects
18Completed
142Permit Applications
318Inspections
₱286MProject Portfolio

Project Progress & Disbursement

Monthly physical accomplishment and financial utilization.

Priority Project Monitoring

High-value and critical infrastructure projects.

PRJ-2026-0018Public Market RehabilitationOngoing
Poblacion · ₱48.6M
78% accomplishedSep 2026
PRJ-2026-0014Mabini Drainage ImprovementOngoing
Mabini · ₱24.8M
64% accomplishedOct 2026
PRJ-2026-0022Rizal Water System ExpansionDelayed
Rizal · ₱31.4M
41% accomplished12 days delayed

Building Permit Pipeline

Applications by processing stage.

New ApplicationsInitial document checking38
Technical EvaluationPlans and engineering review46
For InspectionSite verification required24
For ApprovalFinal approval and release34

Recent Engineering Activity

Latest project, permit and inspection transactions.

ReferenceActivityProject / ApplicantLocationStatus
INS-2026-00842Structural Inspection CompletedABC Commercial BuildingPoblacionCompliant
PER-2026-01428Building Permit EvaluationMaria Santos ResidenceSan JoseIn Review
PRJ-2026-0018Progress Billing ValidatedPublic Market RehabilitationPoblacionFor Approval

Municipal Projects

Infrastructure projects, budgets, contractors and accomplishments.

46Total Projects
28Ongoing
18Completed
4Delayed
₱286MPortfolio
Planning6
PRJ-2026-0028Municipal Hall AnnexDetailed Engineering Design
₱42.8MPoblacion
Ongoing28
PRJ-2026-0018Public Market Rehabilitation78% Accomplished
₱48.6MSep 2026
PRJ-2026-0014Drainage Improvement64% Accomplished
₱24.8MOct 2026
Delayed4
PRJ-2026-0022Water System Expansion12 Days Delayed
₱31.4MRizal
Completed18
PRJ-2026-0004Barangay Health Station100% Completed
₱8.6MJun 2026

Project Registry

Complete municipal infrastructure project information.

CodeProjectTypeLocationContractorBudgetProgressStatus
PRJ-2026-0018Public Market RehabilitationBuildingPoblacionBuildRight Construction₱48.6M78%Ongoing
PRJ-2026-0014Mabini Drainage ImprovementDrainageMabiniPrimeworks Builders₱24.8M64%Ongoing
PRJ-2026-0022Rizal Water System ExpansionWater SystemRizalAquaBuild Corporation₱31.4M41%Delayed

Project Milestones & Step Setup

Define reusable or project-specific milestone steps and monitor actual completion.

46Projects with Milestones
286Total Configured Steps
198Completed Steps
62In Progress
26Delayed Steps

Milestone Step Setup

Create the ordered steps that will be applied to a selected project.

1
2
3
4
5

Project Milestone Monitoring

Configured steps, planned dates, progress and current status.

Public Market RehabilitationPRJ-2026-0018 · Building Construction Standard Steps78% Overall
Site PreparationCompleted · Apr 18
Foundation WorksCompleted · May 12
Structural Works88% · Due Jul 30
FinishingPlanned · Aug 1
TurnoverPlanned · Sep 15
Mabini Drainage ImprovementPRJ-2026-0014 · Drainage Project Standard StepsAt Risk
Survey & LayoutCompleted
ExcavationCompleted
Line Installation62% · +4 days
BackfillingPending
Final InspectionPending
ProjectCurrent StepPlanned EndActual ProgressResponsible TeamVarianceStatus
Public Market RehabilitationStructural WorksJuly 3088%Project Team Alpha-2 DaysOn Track
Mabini Drainage ImprovementDrainage Line InstallationAug 1562%Project Team Bravo+4 DaysAt Risk
Rizal Water System ExpansionPipeline InstallationAug 3041%AquaBuild Team+12 DaysDelayed

Project Assets & Physical Count

Register assets, capture geolocation, assign custodians and conduct physical counts.

1,284Total Project Assets
1,126With Geolocation
1,042Counted This Cycle
186Pending Count
12With Variance

Asset Geolocation Map

Project assets plotted using captured latitude and longitude.

Heavy EquipmentTools / InstrumentsOperational AssetVariance / Attention

Physical Count Sessions

Ongoing and recently completed asset verification activities.

Public Market RehabilitationCNT-2026-0018 · Count Team AIn Progress
156 of 200 assets counted78%
Mabini Drainage ImprovementCNT-2026-0014 · Count Team BCompleted
84 of 84 assets counted2 variances
Rizal Water System ExpansionCNT-2026-0022 · Scheduled Aug 2Scheduled
0 of 126 assets countedNot started

Project Asset Registry

Assets with location, assignment, latest count and variance status.

Asset No.AssetProjectCategoryCustodianGeolocationLast CountCount ResultStatusAction
AST-ENG-001284Backhoe LoaderMabini Drainage ImprovementHeavy EquipmentProject Team Bravo10.8932, 122.7018Jul 20, 2026MatchedOperational
AST-ENG-001283Total StationPublic Market RehabilitationSurvey InstrumentEngr. M. Reyes10.9018, 122.7094Jul 19, 2026MatchedIn Use
AST-ENG-001282Portable Generator SetRizal Water System ExpansionEquipmentAquaBuild Team10.8861, 122.7182Jun 28, 2026Pending CountOperational
AST-ENG-001281Submersible Water PumpRizal Water System ExpansionEquipmentAquaBuild Team10.8794, 122.7256Jul 18, 2026Location VarianceFor Verification

Contractors & Suppliers

Qualifications, contracts and contractor performance.

BuildRight Construction4 active projects · 92% rating
Primeworks Builders3 active projects · 86% rating
AquaBuild Corporation2 active projects · 79% rating
RoadMaster Development2 active projects · 95% rating
CodeContractorClassificationPCAB LicenseActive ProjectsContract ValueRatingStatus
CON-000184BuildRight ConstructionGeneral EngineeringPCAB-284614₱86.2M92%Accredited
CON-000186AquaBuild CorporationWater SystemsPCAB-290182₱48.8M79%For Review

Building Permits

Applications, evaluations, assessments and approvals.

142Active Applications
38New Applications
46Under Evaluation
24For Inspection
34For Approval
Application No.ApplicantProjectLocationBuilding TypeFloor AreaCurrent StageStatus
PER-2026-01428Maria SantosTwo-Storey ResidenceSan JoseResidential184 sqmTechnical EvaluationIn Review
PER-2026-01427ABC Commercial CenterCommercial BuildingPoblacionCommercial842 sqmFor InspectionScheduled
PER-2026-01422JDC TradingWarehouse ExpansionMabiniIndustrial1,240 sqmFor ApprovalCompliant

Engineering Inspections

Inspection schedules, findings and compliance.

Inspection Result

Record findings and recommendations.

36This Week
18Completed
12Scheduled
6For Reinspection
Inspection No.ReferenceTypeLocationInspectorScheduleStatus
INS-2026-00842ABC Commercial CenterStructuralPoblacionEngr. M. ReyesJuly 20Completed
INS-2026-00841JDC WarehouseOccupancyMabiniEngr. A. LimJuly 21Scheduled

Engineering Documents

Plans, drawings, contracts, permits and technical files.

Engineering Plans428 digital files
Permits & Certificates1,284 digital files
Contracts & BOQ186 digital files
Inspection Photos2,842 digital files
Document No.TitleCategoryReferenceUploaded ByDateVersionStatus
DOC-2026-02842Revised Structural PlanEngineering PlanPER-2026-01428Engr. J. CruzJuly 20v2.0Current
DOC-2026-02840Contractor Billing StatementContract DocumentPRJ-2026-0014Project TeamJuly 19Billing 04For Review

Engineering Analytics & Reports

Project, permit, inspection and contractor reports.

Municipal Project Portfolio Report

Entire Municipality · Year to Date 2026

46Total Projects
₱286MTotal Portfolio
74%Physical Accomplishment
68%Financial Utilization

Projects by Type

Distribution of infrastructure projects.

Project Classification

Year-to-date totals.

Road ProjectsRoad and bridge infrastructure14
Building ProjectsPublic facilities and buildings12
Drainage ProjectsDrainage and flood control8
Engineering System
Record saved successfully.